LANNING OF GAGALEHRI-SAHARANPUR-YAMUNANAGAR

FOUR LANNING OF GAGALEHRI-SAHARANPUR-YAMUNANAGAR (UP/HARYANA BORDER) SECTION NH-73 FROM KM.33.00 (DESIGN CH. KM.35.00 TO 74.640) DESIGN CH.86.855) IN THE STATE OF UTTAR PRADESH UNDER NHDP-IV ON HYBRID ANNUITY MODE

Project Title : 

STATE 

UTTAR PRADESH  

GIVEN TIME 

24 MONTHS 

TIME TAKEN 

27 MONTHS 

START DATE

1ST JANUARY 2018 

END DATE 

31ST MARCH 2020 

COST OF PROJECT 

82.36 CR 

REMARKS 

4 Major Bridges, 4 Minor Bridges, 1 Flyover, 4 VUPs, 5 LVUPs, 2 CUPs, 2 ROBs