Our Complete Projects
Our Complete Projects

BUNDELKHAND EXPRESSWAY BAROLIKHARKA - TO BAKJARIYAT
DEVELOPMENT OF BUNDELKHAND EXPRESSWAY (PACKAGE IV) FROM
BAROLIKHARKA (DISTT. HAMIRPUR) TO BAKJARIYAT (DISTT. JALAUN)
(KM 149+000 to 200+000) IN THE STATE OF UTTAR PARDESH IN EPX BASIS-
CONSTRUCTION OF BRIDGE OVER RIVER BETWA (UP).
Project Title :
STATE | UTTAR PRADESH |
GIVEN TIME | 18 MONTHS |
TIME TAKEN | 21 MONTHS |
START DATE | 20TH MARCH 2020 |
END DATE | 31ST DECEMBER 2021 |
COST OF PROJECT | 124.24 CR |
REMARKS | 1 Major 6 lane Bridge of Length 840 x 2 meter having span length of 60 meter |